12 Câu hỏi ôn thi và đáp án SCRUM MASTER - SCRUM EVENTS

1. A primary presenter at the Sprint Review:

a) Developers.

b) Scrum Master.

>> c) Product Owner.

d) Users asking questions and giving feedback.

2. Who can attend Daily Scrum?

a) Only Developers.

b) Developers and Scrum Master.

c) Developers, Scrum Master, Product Owner.

>> d) Anyone can attend Daily Scrum.

3. When can a Sprint be cancelled?

a) When the Product Owner identifies new requirements.

>> b) When the Sprint Goal becomes obsolete.

c) When the Developers realise they cannot complete the forecasted work.

d) When new users pressurize to start a new Sprint.

4. A Sprint's maximum duration is:

a) 2 weeks.

b) 4 weeks.

>> c) Not more than 1 calendar month.

d) Whatever the Product Owner deems appropriate.

5. The 5th event in Scrum is:

a) Sprint Retrospective.

b) Product Backlog Refinement.

>> c) Sprint. It is a container event.

d) Sprint Planning.

6. The subject matter experts (SMEs) invited for a Sprint Planning session are determined by:

>> a) Scrum Team.

b) Product Owner.

c) Scrum Master.

d) Senior stakeholders.

7. At a Sprint Retrospective, a Scrum Master MUST:

a) Ensure the event takes place.

b) Facilitate and Timebox the Sprint Retrospective.

c) Ensure everyone understands that the purpose is to plan ways to increase quality and effectiveness.

>> d) All of the above.

8. It is best to do Product Backlog estimation during:

a) Sprint Planning

b) Sprint Retrospective.

>> c) Product Backlog Refinement.

d) Scrum doesn't mandate estimation, so it is best avoided.

9. A Sprint Review is the first opportunity for the Product Owner to see the working product Increment.

a) True.

>> b) False.

10. The best length of a Sprint in Scrum is:

a) One week.

>> b) There is no ideal Sprint length. It depends on various constraints and can vary.

c) Two weeks.

d) One month.

11. During a Sprint, the Developers realized that they cannot complete the work selected for the Sprint. Who should review and adjust the work selected?

a) Scrum Team.

>> b) Developers and Product Owner.

c) Developers and Scrum Master.

d) Product Owner and Scrum Master.

12. A new Sprint begins when:

>> a) Immediately after the prior Sprint has concluded.

b) After the Sprint Planning has been completed.

c) Next Monday.

d) Only after the prior Sprint work has been completed.