- Posted by: Tommy Tran
- Thu, 10/03/2022, 14:13 (GMT+7)
- 0 Bình luận
10 Câu hỏi ôn thi và đáp án PRODUCT OWNER-PRODUCT BACKLOG
1. The attributes of a Product Backlog Item are:
a) Description
b) Order
c) Size
>> d) All of the above.
2. Product Roadmap and Product Backlog are prioritized based on the following in the given order:
>> a) Customer needs, Business value, Competition, Partners
b) Business value, Customer needs, Competition, Partners
c) Competition, Customer needs, Business value, Partners
d) Partners, Customer needs, Business value, Competition
3. The following is an example of Value:
a) Return on Investment.
b) New registrations on a travel website.
c) Customer satisfaction score.
>> d) All of the above.
4. Product Backlog Refinement is an activity in Scrum where:
a) Product Backlog Items are created, removed or modified.
b) Estimations are made.
c) Business Value is re-evaluated, and Product Backlog Items are re-ordered.
>> d) All of the above.
5. Any new idea or a new Product Backlog Item is:
a) Added to the Product Backlog.
>> b) Added to the Product Backlog.
c) Rejected by the Product Owner because it disturbs the product goal.
d) Accepted into the ongoing Sprint because it adds business value.
6. The following Scrum artifact is modified during: Sprint Review, Product Backlog Refinement, Stakeholder discussions, User feedback:
>> a) Product Backlog.
b) Sprint Backlog.
c) Increment.
d) Any of the above can be modified at any time.
7. Product Backlog is prioritized by the following accountability in Scrum:
a) Developers
>> b) Product Owner
c) Scrum Owner
d) Scrum Master
8. Product Backlog is updated:
a) Every day
b) When the users ask the Scrum Team to update.
>> c) As and when a change occurs.
d) Never updated after created initially.
9. A Product Backlog Item is:
a) User requirement
b) Product Feature
c) System Enhancement
>> d) All of the above
10. Product Backlog Refinement focuses on:
a) Current Sprint's work
b) Next 6 months' work
>> c) Next few Sprints' work
d) All of the above.
Add Comment