7 Câu hỏi ôn thi có đáp án LEADING SAFE - AGILE PRODUCT DELIVERY

1. Who provides Business Value points during PI planning?

>> a) Business Owners

b) RTE

c) Product Management

d) POs

2. How is spike referred in SAFe?

a) PoC

b) Infrastructure enabler

c) Investigation

>> d) Exploration enabler

3. What does 'Accept' mean in ROAM?

a) Someone takes responsibility to look into it

b) Alternate options have been worked out

>> c) Nothing can be done

d) Risk is no longer valid

4. MVPs are used to evaluate Epic hypothesis

>> a) True

b) False

c) Both True and False

d) None of the above

5. Which is the design thinking technique employed to identify with customers?

a) Personas

b) Gemba

c) Customer profiling

>> d) Empathy maps

6. If a program shows separate feature branches in a System Demo, which practice should be reviewed to address the issue?

a) Test driven development

>> b) Continuous Integration

c) Scrum of Scrums

d) Roadmap creation

7. T or F: It is important to decouple deployment from release to enable releasing upon demand

>> a) True

b) False

c) Both True and False

d) None of the above